SE2 – Longsleddale – Complete

28/02/19

Fibre is now complete up both sides of the valley and all the chambers that have connections are spliced. B4RN will need to return to complete 2 chambers of splicing when the properties are ready.

Enjoy it Longsleddale.

TS Trenching have been taken off for a week or two for emergency work on the New Hutton line, they will be back to complete more of Route 3 as soon as they can. Spur SE302 is complete past the school to its end at Kit Crag and is ready for fibre.