Update – 28th Nov

28/11/18 – Week 13 of the Mint and Sprint build and we are rocketing on. Last Friday, TSTrenching completed the West side of Longsleddale and are now on their way out of the valley along the East side. Mid January and you will see the team emerge looking to dig to those who are ready next.

Headlines

  • SE Route 2 build reaches the end of Longsleddale (Sadgill)
  • another 40 properties now ready for fibre and/or splicing
  • Eon booked to fit Electric meter for Head End on 7th Dec
  • 3 new way leaves arrive for Grayrigg
  • get your dig plan and equipment now for festive holiday grafting (yes, get your family digging while they visit)
  • B4MS hits Westmoreland Gazette front page – Link to article – click here
  • oldest Telephone in the Mint and Sprint about to be used via VoIP (Voice over Internet Protocol)
  • major update of the B4MS website giving you all DIY tips and resources
  • holding pen cheques – if you want them submitting to B4RN e-mail me and I’ll forward them on, I still hold cheques where we have not got clear way leaves too.
  • the offices at Mealbank, kindly on loan by the Procter Family, are nearly to the end of the 6 month period and will be closing soon.

So the message is if your route on this page is in green get digging (link), once you have dug and drilled and have FTU’s fitted please e-mail me – danrobinson@b4ms.org.uk

IMG_5616
Oldest Telephone in the Mint and Sprint about to be used via VoIP (Voice over Internet Protocol)

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s